PROJECT QTS

SCHEDULE

PROJECT END DATE

11-10-2024

QTS Phase 1 – 1175

1 X DS1400           9 X DS3100           FAT test

Phase 1 - 10 SCR and Silencers systems manufactured in stainless steel

Key Dates - 1 no DS3100 and 1 no DS1400 SCR needed for 15/08/2024 ( IF FAT TEST PROCEEDS) 8 no DS3100 & SCR to be delivered to site starting mid October

2024 Structural Steel support frames Fabricated and welded to Structural Engineers specification . Steel Sizes to be confirmed as per spec and drawing supplied by AVK Frame connection details TBC All External steel Support Frame Work to be coated to C4 Standard to prevent corrosion from costal environment. deigned to be stackable to reduce transport costs

SATURDAY 27-07-2024

  • Cut & Roll Silencers 
  • Fabricate Silencers
  • Tidy Up

TARGET

  • Cases Cut & Rolled = 2
  • Fabricate Silencers =  2